Table 5 Final certainty degrees and final assessment result for all the case studies
Case study | Final certainty degrees | Risk level | Recommendations | ||||
|---|---|---|---|---|---|---|---|
Level I | Level II | Level III | Level IV | Level V | |||
ZG | 0.3671 | 0.4880 | 0.1692 | 0.0501 | 0.0174 | II | Maintenance and preservation works are recommended. Detailed analysis and monitoring activities can be considered |
HAG | 0.3887 | 0.3667 | 0.1671 | 0.0070 | 0.0737 | I | Maintenance and preservation works are recommended |
LG | 0.2804 | 0.1999 | 0.3021 | 0.1691 | 0.0671 | III | Minor damages requiring long-term restoration works. More detailed risk analysis is recommended |
CLP | 0.3918 | 0.1903 | 0.1984 | 0.1947 | 0.1220 | I | Maintenance and preservation works are recommended |